Hazelwood Data Center, Confidential Client
Hazelwood, MO
Hazelwood Data Center Expansion, HED
Changing engines in a
moving train.
Detailed phasing keeps data center running during upgrades.
Powerfully done.
An existing enterprise data center for an international financial services corporation was having difficulty cooling its expanding IT load and was reaching both mechanical and electrical capacity. The facility had an unusual configuration, wherein three floors of servers were vertically connected by floor openings and grating, thus dispersing rather than concentrating cold air supply. The upgrade required the data center to effectively double its total power to 10MW while increasing power densities per rack from 2-3kW to 6-8kW. Due to the critical nature of the facility, it had to remain fully operational throughout construction.

HED provided master planning, architectural design, and engineering design services to reach this goal in the form of a two-story addition housing new infrastructure systems within and on the roof. An N+1 redundant generator plant, 2N multi-module UPS systems, and a 2,400-ton water-cooled chiller plant were just a few of the features used to maximize the facility's newly configured 90,000 SF computer room.

The design entailed the complex integration of architectural and engineering elements, with the siting being the immediate priority. To enable detailed phasing, cut-over conversion procedures, and minimize distribution runs, a site adjacent to the entrance was selected. This required a sensitive response compatible with the existing architectural forms and materials.
Results
The 20,000 SF expansion houses new MEP infrastructure.
Photovoltaic cells on the south elevation power the building lighting systems.
The three-level addition was built and the cut-over of mechanical and electrical systems was accomplished while the facility remained fully operational.
The addition replicated the architectural language of the original data center building.
UPS system includes 95% improved energy efficiency.
/1
1
Project Data
Hazelwood Data Center Expansion IDG-DC-26
Thomson Reuters
Hazelwood, MO
PROJECT SCOPE
Renovation
HED ROLE
Design Architect
RSF/GSF
90,000
CONSTRUCTION COST
WND
SUSTAINABILITY LEVEL
HED Standard
YEAR COMPLETED
2011
Project Team
  • Stephen McNeice
    PE
    Principal
    Project Management Leader
    PROJECT MANAGER
  • Toni Asfour
    Managing Principal
    Architecture + Design
    MANAGING PRINCIPAL
  • Chad Fowler
    AIA, LEED AP
    Principal
    Architecture + Design Leader

  • Robert Stein
    AIA, LEED AP
    Principal
    Architecture + Design

  • Thomas Macleod
    AIA
    Associate
    Architecture + Design

  • Robert Buchetto
    Associate AIA
    Associate
    Architecture + Design

  • Eric Speenburgh
    PE
    Associate Principal
    Electrical Engineering Leader

  • John (Jack) McCarthy
    PE, DCEP
    Principal
    Sector Leader

Detailed phasing keeps data center running during upgrades.
Hazelwood Data Center, Confidential Client
Hazelwood, MO
PROJECT DATA
PROJECT TEAM
Changing engines in a
moving train.